Project:   Vans - RV-7   -   VIEW REPORTS
Total Hours:1460.9
Total Flight Time:
Start/Last Date:Jun 24, 2017 - No Finish Date
Engine:Lycoming IO-360
Propeller:Whirlwind 200RV
Panel:Advanced Flight Systems Avionics
 
Friendly URL: https://eaabuilderslog.org?s=DaveBellairs

Home or Last Project Picture

Dec 13, 2023     Pitot tube bracket - (3 hours)       Category: Wings
Fabricated a bracket to secure the pitot lines in the wing. Installed a couple nutplates to hold the Adel clamps and attempted to install in the wing. Difficult if not impossible to tighten the Adel clamps with one hand. Will try and rivet the bracket to the rib then tighten the clamps. Still unsure if this is going to work.


 